KDC CORPORATE OFFICE DEVELOPMENT DURING THE PAST FIVE YEARS
                                                                              KDC'S CORPORATE FOCUS



 CORPORATE TENANT  LEED  SIZE  SCHEDULE  STATUS  TRANSACTION TYPE
               INCLUSION / DIVERSITY                                                    PROJECT SAFETY                                                      SUSTAINABILITY
 State Farm Regional HQ at CityLine  2,100,000 SF  42 Months  Complete: 9,000 Employees  NNN Lease / Open Book


 Raytheon at CityLine  489,000 SF  15 Months  Complete: 1,500 Employees  NNN Lease / Open Book

 Toyota Motor North America HQ at Legacy West  2,100,000 SF  30 Months  Complete: 7,000 Employees  At Risk Dev Fee


 Liberty Mutual Insurance at Legacy West  1,100,000 SF  26 Months  Complete: 5,500 Employees  NNN Lease / Open Book

 JPMorgan Chase Regional HQ at Legacy West  1,500,000 SF  21 Months  Complete: 6,000 Employees  At Risk Dev Fee / Land Owner


 FedEx Office HQ at Legacy West  265,000 SF  12 Months  Complete: 1,100 Employees  NNN Lease / Open Book

 State Farm Data Centers (2)  Pending  300,000 SF  16 Months  Complete: 100 Employees  NNN Lease

 Frost Bank HQ  500,000 SF  24 Months  Complete: 1,700 Employees  NNN Lease / Open Book


 Independent Financial  159,000 SF  12 Months  Complete: 400 Employees  At Risk Dev Fee

 Pioneer Natural Resources HQ  1,125,000 SF  25 Months  Complete: 2,500 Employees  NNN Lease / Open Book


 Epic Phase I  250,000 SF  24 Months  Complete: 2,200 Employees  At Risk Dev Fee
                                                                                                                                                                              TOYOTA - LEED PLATINUM
 Uber, Epic Phase II  500,000 SF  30 Months  Underway (2022 Completion): 3,000 Employees  At Risk Dev Fee  RECORDABLE INCIDENT RATE - 1/2 OF INDUSTRY AVERAGE


 Credit Suisse  400,000 SF  15 Months  Underway (2020 Completion): 3,900 Employees  At Risk Dev Fee

 State Farm at Park Center Regional HQ  1,750,000 SF  39 Months  Underway (2020 Completion): 9,000 Employees  Fee Dev / Open Book

 Baylor Scott and White  Pending  300,000 SF  23 Months  Complete: 1,500 Employees  At Risk Dev Fee


 SRS Distribution  Pending  100,000 SF  14 Months  Complete: 500 Employees  NNN Lease

 Sammons Financial Group  Pending  217,000 SF  16 Months  Underway (2021 Completion): 700 Employees  At Risk Dev Fee


 Raytheon McKinney  Pending  200,000 SF  14 Months  Underway (2021 Completion): 500 Employees  At Risk Dev Fee

 TOTAL LAST 5 YEARS  13,355,000 SF  22 MONTHS AVG  56,100 EMPLOYEES