Page 37 - Zero is Possible - Volume 2
P. 37
Surma Cement Plant
Water
From flush to fresh BANGLADESH
Opportunity Results Cement
The backwash process at • Massive water savings:
Surma’s water treatment Saved 7,300 m³ of water
plant (WTP) was wasting annually, cutting nearly
significant amounts 2% of the plant’s daily
of water, offering an freshwater use
opportunity to recycle • During the rainy season,
it and improve water our system also captures
conservation. rainwater, boosting
conservation efforts
Solution
Developed an in-house Mohammad Iqbal
system to collect drained Chowdhury
water and reintroduce CEO
it into the plant’s water
system, maximizing
resource efficiency.
Mohammad Abdul
Matin
Head of HSE
29