Page 46 - Zero is Possible - Volume 2
P. 46
Paulding Cement Plant
Water
UNITED STATES Cement Making zero freshwater
discharge a reality
Opportunity Results
Plant centers around two This was accomplished
long wet kilns making it a by controlling the level
large consumer of water. of the large reservoir
through the automation
Solution of a secondary outfall
Paulding team improved location.
the management of This solution substantially
Jaime Hill stormwater by fully decreased freshwater
3
Region Head segregating the quarry withdrawal 100 m /month
North America dewatering activities from in 2023.
the stormwater collected
in a small pond.
Investment: 120 kCHF
Timeline: 5 months to
design and install
Michael LeMonds
Vice President ESG and
Chief Sustainability
38