Page 28 - Untitled-1
P. 28

THE TRACKING PHASE                                    7

                      Figure 1.1a Flow Diagram:
            Steps toward Developing the Baseline Plan

                                   RESOURCES           RESOURCE
                                    AVAILABLE           LOADING
                                                           PLAN

            MILESTONE      TASK     LEVELED            ADJUSTED
            SCHEDULE   SCHEDULE    SCHEDULE            SCHEDULE

PROJECT WORKSCOPE      TASKS                           BASELINE
                                                          PLAN
OBJECTIVES  (WBS)      DEFINITION

               COST    WK. PKG.                        ADJUSTED
            ESTIMATE   BUDGET                           BUDGET

                                                       CASH FLOW
                                                            PLAN

      Scope change is a natural situation in projects. This is only a problem if it
   is not managed. Then it becomes scope creep, a really nasty situation. It is
   essential to establish a method of change control. When changes are intro-
   duced into the workscope, you must define the specific tasks that will be
   added, changed, or deleted, and the effect of these changes on time, re-
   sources, and costs. One rule to follow is that the working budget is always a
   task budget. The total project cost is the sum of the budgets for each task
   (plus contingency and margin). The task budget does not get adjusted un-
   less there is a defined change in the task list. See Chapter 7.1 for Change
   Control and Scope Management.
• Track Work Progress
   If you follow the defined process up to this point, you should derive signif-
   icant benefits from your planning investment. From here on out, the
   process requires extreme diligence, to continue the payoff. It is fair to say
   that there are those who will not want to make the commitment to track
   the work in detail, or to track all of the project elements. For instance, you
   23   24   25   26   27   28   29   30   31   32   33