THE TRACKING PHASE                                                            9

   actual cost (ACWP—Actual Cost of Work Performed) is compared to the
   earned value (BCWP) to compute the CV. You’ll find extensive coverage of
   earned value analysis and performance management in Section 8.
• Evaluate Performance
   Use your actuals measurements to track SV and CV and to analyze when
   progress does not support the plan. Using WBS frameworks, you can ana-
   lyze the data at a high level. Where an out-of-tolerance condition exists, drill
   down to the details to find the source of the anomaly.

      The data can be analyzed in tabular or graphic formats. The data can be
   produced either directly from the CPM program, or data can be exported to
   other applications for eventual presentation. The latter option allows for com-
   bining data from multiple sources or for adding special formatting or notation.

      Figure 1.1b illustrates a Cost/Schedule Status Report. Figure 1.1c com-
   pares BCWS, BCWP, and ACWP. Figure 1.1d shows cost (CPI) and sched-
   ule (SPI) performance trends.
• Forecast, Analyze, and Recommend Corrective Action
   There’s no sense in collecting all of these data, analyzing, and evaluating, un-
   less you’re going to do something about the results. Use these data to fore-

                            Figure 1.1b CSSR Report

           Project Workbench – evtes102.aca – [Cost Schedule Status Report [CSSR]]
File Edit View Setup Operations Window Help

Phase One                BCWS BCWP ACWP                      SV        CV BAC          EAC    VAC

       Sort by Category  200.0             200.0    250.0          .0  –50.0    200.0  250.0  –50.0
                         120.0              80.0    100.0     –40.0    –20.0    200.0  220.0  –20.0
Task Name                120.0              40.0              –80.0             200.0  200.0
 Phase One                                           40.0                   .0                     .0
 Wk Pkg A                200.0             200.0                   .0           200.0  200.0
 Task 1                  120.0             160.0    200.0       40.0        .0  200.0  120.0       .0
 Task 2                                              80.0               80.0                   80.0
 Task 3                  500.0             500.0                   .0           500.0  500.0
 Wk Pkg B                     .0                .0  500.0          .0       .0  500.0  500.0       .0
 Task 10                                                 .0                 .0                     .0
 Task 11                 300.0             300.0                   .0           500.0  500.0
 Phase X                                            300.0                   .0                     .0
 Task 20                 500.0                  .0           –500.0             500.0  500.0
 Task 21                 200.0                  .0       .0  –200.0         .0  200.0  200.0       .0
 Phase Y                 100.0                  .0       .0  –100.0         .0  100.0  100.0       .0
 Task Y                  100.0                  .0       .0  –100.0         .0  100.0  100.0       .0
 Phase Z                                                 .0                 .0                     .0
 Task 30
 Task 31
 Task 32
 Task 33

<F8> Modify <Inc> – Insert <Del> – Delete
   25   26   27   28   29   30   31   32   33   34   35