b). ACTION PLAN ITEMS (POWER)
Actual Actual
Target Actual
Description 2022- 2020-21 2021-22 2022-23
23 (Apr- (Apr- (Apr-Oct)
Oct) Oct)
1 Energy consumption in MU 12.04 13.26 14.02
(w.r.t Last year) (-5%) 25.60 (Apr- (Apr- (Apr-
Sept) Sept) Sept)
2 Provision of sanctioned 3 0 2 0
Escalators
3 Provision of sanctioned Lifts 7 0 2 1
4 Energy auditing of major
load centres and pumping 20 0 1 8
installations
5 Green Co. rating for
1 (SC
office/station buildings 1 0 0 under
(ensure electrical process)
compliance)
6 Provision of 5/10 kWp ON
Grid solar plant at D/E cat. 5 0 0 0
stations (No of Stations)
7 New/Replacement of
conventional geysers by
solar geysers and 3 1 0 3
repair/reconditioning of
existing solar geysers
8 Solar Based Street lights for
a) Colonies b) Training 8 0 0 8
Institutes
9 Energy efficient pumps in
place of old in-efficient 10 8 3 6
pumps