Page 234 - GM E-BOOKLET 2022
P. 234
2. GENERAL PERFORMANCE
2.1 GENERAL PERFORMANCE PARAMETERS
Achieved
22-23
S. No Description 22-23
Target
(up to Oct-22)
Accidents on Elect loco/Crew
A/C
1 (a)Collisions Nil Nil
(b)Derailments Nil Nil
(c)SPAD Nil Nil
2 Stallings on account of crew Nil Nil
Loss of punctuality of trains due
3 Nil Nil
to crew mismanagement
4 9 Hrs rule Wheel - 86.3
implementation Movement
in % CMS 60 59.7
5 SEC (Goods) / Month (Aug’22) 3.30
3.68
SFC (Goods) (Aug’22) 2.00 2.71
Pre-Arrival Detention in Minutes
6 (Avg on Divn) excluding Zonal 15’’ 20.1
interchange point.
Periodical rest @ 30 hrs given to
7 4
running staff 4.0
CMS booking in fetch as per
8 100 96.2
rule (%)
9 Energy feeding in CMS (%) 100 94.6
10 % of Utilization of running hrs 90 95.6
No. of trip inspections of Locos
11 300 290
in Trip Sheds
12 Electric Loco failures 162 130
13 Diesel Loco failures 57 44
232