Page 140 - CRS E-BOOKLET 2022
P. 140
138
Fig: Point shifting work at AMQ
Provision of Disconnector assembly on top side of the Lightning Arrester (LA):
As per revised SMI no. TI/SMI/0048
(Rev. 1) dated: 23.07.2021, the
Disconnector assembly of LA
should be repositioned at the Top
of the LA. The Division has taken-up
the work and replaced out of 419
Nos 414 LA’s modifications
completed. Fig: LA modification
Energisation of Switching stations between KHNP-LTRR in VKB-PRLI section:
The energisation of switching stations (Halbarga/SSP, Bhalki/SSP,
Kamalnagar/SSP, Udgir/SSP and HER/SSP) in KHANAPUR (KHNP) – LATUR
ROAD (LTRR) BG Single line section of VKB-PRLI was done on 28.09.2022, after
duly obtaining the EIG sanction vide sanction number 2209036,
Dated:24.09.2022.
Fig: PCEE/EIG Statutory Inspection
between KHNP-LTRR
Charging of KKMP/SP @ PDPL-NZM section:
After charging of MRTD/TSS in PDPL-NZB section, there is no SP for separation
of supply between KPHI and MRTD TSS feeding. Now new SP has been
constructed by RE department at KKMP and same was charged on
07.07.2022 after duly completing all the works and obtaining the EIG
sanction vide sanction no.2207013, dated 05.07.2022. Previously feeding of
Morthad TSS was extended up to KPHI feeding post.