Page 6 - Focus - Spring 2022
P. 6
Project Focus
Millbrook Park Phase 6B
Kane was appointed by Main Contractor, Bennett Construction,
to deliver the £13.7 million MEP Design and Build contract at The 18-month contract included
Millbrook Park Phase 6B. The residential project consisted of the Low Temperature Hot Water
257 apartments contained within 2 blocks. The residential (LTHW) requirements which is
units included a mixture of Private Sale, Social Rent, and served from a site wide district
Intermediate tenure. heating network, with an intake
We engaged with the client plantroom located within each
at Stage 3 design through Block. Each block has a Car Park
to stage 6 design, providing located on the Lower Ground
construction solutions at every Floor where we installed a
stage. We initiated Point Cloud mechanical smoke extract system.
Survey enabling us to carry The space heating requirements
out our works ahead of other within each Private dwelling are
contractors on site, providing served by Underfloor Heating, with
significant programme savings. Radiators being installed within the
Social and Intermediate dwellings.
Other works included switch
Our prefabrication team rooms, lighting control systems in
designed and manufactured the car park area, fire alarms and
utility PODs for the project which access control.
was a huge success enabling the
project team to deliver 18 flats per A very well done to the entire
week at its peak. project team.
6 KANE FOCUS