          TWO BERTHS (9 & 10) AT RAS AL-KHAIR SEAPORT

          DESIGN & BUILD CONTRACT




          PROJECT DETAILS                                                                                                          PROJECT OVERVIEW:
          Location: Ras Al-Khair, Saudi Arabia                                                                                     At EDECS, we take pride in overseeing the project at Ras Al-Khair Seaport, Saudi Arabia, where our expertise is

          Name of Client: SEAPA - Seaports Authority, Kingdom of Saudi Arabia                                                      showcased through  dredging  operations,  construction  of a  substantial  gravity-type quay wall, and  meticulous
          Role in Contract: Main Contractor                                                                                        attention to detail in every aspect of the endeavor. The project at Ras Al-Khair Seaport involves dredging over 3.5
                                                                                                                                   million cubic meters to level the basin and trenches, with reclamation exceeding 1.5 million cubic meters. Additionally,
          SCOPE OF WORK                                                                                                            a 900-meter-long, 18-meter-deep gravity-type quay wall will be constructed using concrete blocks weighing up to
                                                                                                                                   120 tons each. Other tasks include building a jetty for a 500-ton crane, soil improvement, and various installations.
                                         Consultant Name: Lievense Arabia
             MARINE                      Contract Duration: 29 Months                                                              Under a Design & Build contract, the project spanned 29 months, starting in July 2014 and completed in December
                                         Project Type: Concrete Blocks Quay Wall and Dredging                                      2016. We remain committed to delivering exceptional results that exceed expectations.