 WESTERN EDGE RETAINING WALL 480M FOR BASIN 2,

 AL SOKHNA SEAPORT




 PROJECT DETAILS
 Location: Ain Al Sokhna, Egypt  PROJECT OVERVIEW:
            EDECS, as the main contractor, is responsible for constructing a 480-meter quay wall of diaphragm type with a tie rod
 Name of Client: DP world Sokhna
            system for Basin 2 at Al Sokhna Seaport, Egypt. This includes essential furnishings such as fenders, bollards, ladders,
 Role in Contract: Main Contractor
            and an anchoring system. A barrette wall will also be constructed to secure the tie rod system. MEP works and road

            construction for the area behind the quay wall are also part of the scope. The project involves significant quantities,
 SCOPE OF WORK
            including 480 front and back diaphragm wall panels, and extensive concrete and pavement installations.
 Consultant Name: Pacer Consultants
 INFRASTRUCTURE  Contract Duration: 13 Months
 Project Type: Infrastructure Work
 Consultant Name: Pacer Consultants
 MARINE  Contract Duration: 13 Months
 Project Type: Diaphragm Wall Quay Wall