the President or the funding agency by the Project Leader. When the request
                           is justified, the request may be granted.
                                  With respect to the LIB, transfer of funds from one line-item budget to
                           another may be allowed as long as the amount does not exceed 15 percent of

                           the line item. When the needed realignment exceeds 15 percent of the line
                           item, the project leader needs to request for realignment of funds to the VP-
                           RDET for internally funded projects and to the funding agency for externally funded
                           projects. Only upon approval of the request shall the allocation change be
                           formalized and implemented.
                       e. Research Project Reports
                                  The project leader shall submit a quarterly Progress Report in the prescribed
                           format. The report shall be the basis of monitoring and evaluation of the progress
                           of project implementation.
                           The progress of project implementation with respect to the plan, based
                           accomplishment targets or deliverables and specified in the approved project

                           proposal.
                                  Likewise, a semi-annual Audited Financial Report (AFR) shall be prepared
                           and submitted
                           to the VP-RDET and the funding agency by the ISU Accounting Department.
                           However, a Project Leader may request for an updated AFR as deemed necessary.
                       f. Transferring project leadership
                                  Project leadership may be transferred to another upon request or
                           incapacity of the incumbent or when University management finds it necessary.
                           When the Project Leader leaves for at least three months, he should recommend

                           someone to take his place while he is out. To ensure the smooth implementation of
                           the project, the substitute leader should have the same field of specialization.
                       g. Project monitoring and evaluation
                                  A systematic monitoring and evaluation (M&E) shall be implemented for
                           all research projects. The evaluation shall be based on the detailed action and
                           financial plan as embodied in the approved research proposal. For the purpose,
                           prescribed M&E forms shall be used. The cumulative progress of the project
                           shall be closely monitored to ensure that project outputs and deliverables shall be
                           attained on time as envisioned and scheduled in the research proposal.
                       h. In-House Reviews
                                  An integral component of the M&E of ongoing and terminated researches

                           shall be the conduct of a regular R&D Agency In-House Review (AIHR) by the
                           University. This shall be conducted once a year. The AIHR shall be done in
                           coordination with the pre-AIHR reviews of the different ISU campuses and clusters.
                           A campus may opt to conduct other reviews as it may see fit.