12. Disposal of Scrap:
Proporti Achieved
Target for %
Scrap Type 2019-20 onate during Improvement
Disposal target 2019-20
1
(M. Tons) Ferrous 173 115.3 125.5 8.85%
Non
Ferrous 8.5 5.6 3.367 -39.8%
13. Progress of Works:
Name of the Work Year of Sanctioned Cum. Funds
Sanction Cost (Cr) Expenditu available
re (Cr) (Cr)
Additional Infrastructure PWP 18.81
facilities for holding 100 PB No.571 (RE cost: 28.32 2.32
locos. of 19-20, 31.91)
PH:4200
Augmentation of PWP PB 9.61
DEMU/MEMU Car shed No. 602 of (RE Cost: -- 2.5
for holding 16 Coach 2019-20. 12.83)
DEMU/MEMU rakes PH:4200
14. Assistance Required:
Filling up of AMM Post: It is requested for filling up of AMM post vacant from
08-02-19 at DLS/MLY at the earliest as much difficulty is experienced in
maintenance of locos due to non-availability of critical items.