Page 9 - safety
P. 9

Injured person shifted to ambulance for             Hyderabad division medical team giving
                            treatment                               treatment to injured passengers

         9. Safety Drives:

         The following 30 safety drives have been conducted on the division upto October 2021, involving officers
         and supervisors. Irregularities brought out were rectified and concerned staff  were counseled suitably.

          S.  Month &                             Subject                                      Period
         No      Year                                                                    From           To
          1    Jan-21    Ensuring safety while executing works adjacent to running  02.01.2021      16.01.2021
                         lines.
          2    Jan-21    Winter season precautions                                   21.01.2021     19.02.2021
          3    Jan-21    Maintainance  of  Track at  Fish  plates  joints,  Glued  joints  28.01.2021   11.02.2021
                         and major Bridges with ballasted deck.
          4    Jan-21    Ensure  proper  insulation  is  available/provided  for  the  28.01.2021   11.02.2021
                         rodding at all manned LCs
          5    Jan-21    Ensuring availability  of First aid box with standard list of  28.01.2021   11.02.2021
                         Medicines
          6    Feb-21    Maintenance of points and crossings                         01.02.2021     15.02.2021
          7    Feb-21    Maintenance of Track and Points & Crossings in yards as  09.02.2021        10.03.2021
                         well as strict observance of rules in shunting.
          8    Mar-21    Prevention of LC Gate open cases                            01.03.2021     15.03.2021
          9    Mar-21    To prevent cases of Fire in trains                          16.03.2021     14.04.2021
          10   Mar-21    Dry vegetation at Railway Installations                     22.03.2021     05.04.2021
          11   Mart-21  Precautions to be taken while backing the train              23.03.2021     06.04.2021
          12   Mar-21    Rolling down of Locomotives/train                           23.03.2021     06.04.2021
          13   Mar 21    Massive  drive  against  smoking  and  carriage  of  25.03.2021            30.04.2021
                         inflammable material through rail
          14   April-21  Prevention of SPAD                                          01.04.2021     15.04.2021
          15   April-21  Summer weather precautions                                  29.04.2021     13.05.2021
          16   April-21  Prevention of Yard Derailments                              29.04.2021     13.05.2021
          17   May-21  Prevention of Yard Derailments                                01.05.2021     15.05.2021
          18   May-21  Prevention  of  derailments  of  freight  trains  while  25.05.2021          08.06.2021
                         entering/leaving stations and yards.
          19   May-21  Safe securing & Packing of Goods Rake                         28.05.2021     27.06.2021
          20   May-21  Safety while operating Track Machines                         27.05.2021     10.06.2021


                                                                                                    Page 9 of 12