DETAILS OF ROBs IN SC-MOB SECTION OF HYB division
SI.No Location Station Contact wire Ht.in Mts
1 613/26 - 613/28 RKO 5.50
2 613/25 - 613/27 RKO 5.54
3 612/40 - 612/42 AMQ 5.29
4 612/39 - 612/41 AMQ 5.25
5 611/21 - 611/23 CVB (SC END) 5.75
6 611/21 - 611/23 CVB (SC END) 5.72
7 611/22- 611/24 CVB (SC END) 5.47
8 611/22- 611/24 CVB (SC END) 5.44
9 610/35 - 610/37 CVB (MOB END) 5.50
10 610/39 - 610/36 CVB (MOB END) 5.45
11 610/36 - 610/38 CVB (MOB END) 5.47
12 610/11 - 610/13 ALW 5.34
13 610/12 - 610/14 ALW 5.38
14 602/33 - 606/35 BMO - GDPL 5.75
15 602/34 - 602/36 BMO - GDPL 5.76
16 597/3 - 597/7 GDPL - GWV 5.75
17 597/4 - 597/6 GDPL - GWV 5.76
18 597/7 - 597/9 GDPL - GWV 5.74
19 597/6 - 597/8 GDPL - GWV 5.76
POWER LINE CROSSINGS Details Secunderabad-Monoharabad Section
Clearance from OHE to
Section
Sl.No KM.no/ Location Between Type of Voltage bottom of Power line
Xing conductor
Stations
( in meters)
UP 609/21-23 132 KV 3-phase Double
1 ALW-BMO 9.16
DN 609/22-24 circuit line
UP 612/23-25 132 KV 3-phase Double
2 AMQ-CVB 6.68
DN 612/22-24 circuit line
UP 601/35-37 220 KV 3-phase Double
3 GDPL Yard 11.12
DN 601/36-38 circuit line(I)
UP 601/35-37 220 KV 3-phase Double
4 GDPL Yard 10.78
DN 601/36-38 circuit line(II)
UP 601/27-29 132 KV 3-phase Double
5 GDPL Yard 7.88
DN 601/28-30 circuit line
UP 599/13-15 132 KV 3-phase Double
6 GDPL-GWV 5.36
DN 599/14-16 circuit line
UP 595/6-8 132 KV 3-phase Single
7 GWV-MED 5.53
DN 595/5-7 circuit line
Page 12 of 13