Page 9 - CRS - Elec
P. 9
VI. Tower Car Position :
Tower car 8-Wheeler ICF make No. 4193 [DETC-190042] commissioned and being
utilised by KCG depot.
VII. Details of POWER BLOCKS Availed as on 30.09.2021
Availed Hrs of Power Hrs of Power Percentage
Power Block Asked
Block Asked Block Issued
TRD 303 300 339 323 95%
Local Block 0 0 0 0 0%
Engg. 26 26 27 27 100%
RVNL 15 15 43 43 100%
VIII. Plan Head:
The plan head expenditure for 3700 and revenue expenditure for TRD/HYBunit is submitted below:
Figures in ‘000
BG/RG
YEAR Allocation Primary unit Expenditure Percentage
SL
PU 28 1537 794 51.65
2020-21 Revenue PU 32 3406 2984 87.61
Revenue PU 28 1887 855 45.31
2021-30upto
SEPT PU 32 3736 3415 91.4
Primary Sanctioned Percent
Allocation BG Expenditure
unit Cost age
PH-3700 [2020-21] LSWP 1 22789 0 0
PH-3700[2021-22] LSWP 1 22789 0 0
IX. RAILWAY ELECTRIFICATION Works In Progress :
S.No Major section Section being electrified RKM TDC
1 SC-DHNE GLY-MBNR 26 DEC-2021
2 SC-DHNE KRNT-DHNE 54 FEB-2022
3 SC-MUE NZB-BDHN 27 FEB-2022
4 SC-MUE MOB-KMC 68 MAR-2022
5 SC-MUE JKM-MUE 83 MAR-2023
6 SC-MUE KMC-NZB 52 JUNE-2023
7 SC-DHNE GWD-KRNT 55 JUNE-2023
8 SC-DHNE MBNR-GWD 75 SEPT-2023
Page 9 of 13