1. Progress of MOU items
Progress Remarks
Sl Key Performance Unit of
No Indicator Measurement Target up to
Feb‟21
Progress of Track --
1 CTR Units 4.00 5.425
Renewals
Deep Screening of --
2 Nos 25.00 55
Turnouts
Achieved highest one
Deep Screening of day progress of 2.700
3 Kms 40.00 76
Plain Track Km with two BCM
machines.
Removal of --
4 Permanent Speed Nos 2.00 2.00
Restrictions
Division has exceeded
Elimination of
5 Manned of Level Nos 10 14 the target for the year
Crossing Gates 2020-21 and saved
about 42 Manpower.
(In 2019-20 Rail / Weld
41 %
5 % failures were 17 Nos
Control of Rail / reduction
6 % Reduction and in 2020-21 Rail /
Weld failures over last
over last Weld failures are 10
year
Nos)
2. Performance of track renewal works:
Progress up
S.No Item Unit Target
to Feb‟21
Km in CTR
1 Track Renewal 7.88 5.465
Units
2 Through Rail Renewal (P) TRR(P) Tkm 7.00 5.930
3 Through Sleepers Renewal (P) TSR(P) Tkm 5.00 5.00
4 Through Fitting Renewal - TFR Tkm 45.00 26.80
5 Deep Screening of Ballast Tkm 70.00 76.00
6 Deep Screening Points & Crossings Nos 105.00 55.00
7 TTRR - Curved Switches Nos 15.00 28.00
8 TTRR - CMS X'ings Nos 2.00 28.00
9 Through Formation Treatment - TFTR Tkm 31.00 7.910
10 Glued Joints Nos 25.00 94.00