Page 11 - Electrical TRD - CRS
P. 11

Date of
                 Electrified Sections           RKM           TKM         Main Route
                                                                                          Commissioning
               SC-FM                          16.021           40.740   SC - DHONE        14.02.2004
               SC- STPD - MJF –MLY            11.617           15.973   SC - MUE          10.10.2010
               MJF-BMO                        12.690           31.683   SC – MUE          14.03.2018
               BMO-MED                        14.950           34.439   SC -  MUE         08.07.2019
               MED- MOB                       13.080           15.968   SC -  MUE         07.10.2020
               TOTAL                          68.358         138.803


             RE Works In Progress :


                 Sl. No       Jurisdiction        RKM          TKM                  Remarks
                   1.           FM - UR          13.695           32.897    RE Work under progress by
                   2.         UR - MBNR           75.5          189.750                RVNL.
                   3.         MOB - MUE            227          281.0
                   4.        NZB - Jagityal          93.0      103.0
                   5.        JKM - BDHN            20.0          25.0       100% RE work executing by
                   6.         MOB - KPHI          151.0         170.0     CORE/ALD & Construction/SC.
                   7.       MBNR - DHNE           181.0         225.0
                   8.         DKC - KSN           70.0            70.0
                   9.          GWD-RC              60.0           56.2
                                 Total          891.195   1152.847


                  2 new TSS @ Manoharabad & @Timmapur :  work under progress by M/s. RVNL.





                                                             11