Risk Assessment - 10. East Kirkby Farm Return to contents page
RISK ASSESSMENT
Risk Assessment NUMBER East Kirkby Chicken Farm Risk Assessment Number 17
TITLE
DESCRIPTION OF TASK
LOCATION Quarrington ASSESSOR Steve Bennett REVISION No. 001
ASSESSMENT TEAM Steve Bennett N/A N/A N/A N/A
(List all people involved)
Date of Initial Assessment 01/03/2023 Next Review Date 01/03/2024
Reviewed Date: 01/03/2024 Reviewed By: Steve Bennett
Key: S = Severity P = Probability RI = Risk Index S x P = RI Risk Index
P
S Severity Description P Probability (how likely is the occurrence) S 1 2 3 4 5
1 No damage / no injury 1 Practically impossible / highly unlikely 5 5 10 15 20 25
2 Damage to vehicle / damage to 2 Not likely but small chance of happening 4 4 8 12 16 20
environment / no injury
3 Minor injury / illness (occupational) 3 Possible 3 3 6 9 12 15
4 Major injury / illness (occupational) 4 Likely therefore assume can happen 2 2 4 6 8 10
5 Fatality 5 Very likely therefore assume will happen 1 1 2 3 4 5
Section 1 Risk Index Section 2 Section 3 Section 4 Risk Index
Description of the Without What/ Who is Arrangements required to Person responsible for With Control
hazards and risks Control at risk adequately control the risk implementing and monitoring Measures
the controls
S P RI S P RI
Satellite navigation
devices for cars are NOT to be used The driver or operator will have
Drivers in any Beauparc Truck. full responsibility of operating or
Other Road Satellite Navigation using a truck satellite navigation
Satellite Navigation 5 4 20 Users. devices designed for trucks may be system. Car satellite navigation in 5 3 15
Devices Bridges used at the operators risk however a truck is forbidden.
Cars / Trucks Width they must contain the correct
openings information data for the vehicle The General Manager will
you are driving. They may only be monitor and implement this
used for the final 1 mile of the procedure.
journey destination.
Drivers
Other Road The only map book to be used is a The General Manager will
Users. map book that displays bridge monitor and implement this
LGV Map Book 5 4 20 Bridges heights, bridge widths and weight. procedure. 5 2 10
Width
openings
17