Chapter 4 ESTIMATING 231
C
l�L ONSTRUCTION
YOUR CO NPLET E DESJG N-8UJLDER
PROJECT : ACME MANUFACTURING BUDGET EHTIIMTE
Division Heading/Phase Cost
BUDGET SUMMARY
1000 General $117000
2000 Site $112900
3000 Concrete $92500
4000 Masonry $39400
5000 Metals $68600
6000 Woods & Plastics $11800
7000 Thermal/Moisture Protection $58500
8000 Doors/Windows $51200
9000 Finishes $87300
10000 Specialties $4800
13000 Special Construction $197300
15000 Mechanical $95000
16000 Electrical $75000
CONSTRUCTION BUDGET COST $1,011,300