Page 257 - TCDB combined Book
P. 257

234                       The Complete DESIGN BUILDER



                l�L   CONSTRUCTION

                 YOUR   CO NPLET E  DESJG  N-8UJLDER

                PROJECT : ACME MANUFACTURING                                  BUDGfT fHTIIMTf


               Division           Heading/Phase                  Quantity/Unit Cost               Cost

               5000        Metals


                           Miscellaneous

                                                          Stairs = 2x18R=36 risers @ $250               $8000

                                                          Bollards (4)                                  $1000

                                                          Ladder (1)                                     $800


                                                                                   Metals             $68600

               6000        Wood and Plastics


                           Rough carpentry

                                                          Roof parapet = 240 lf @  $6.00                $1500

                                                          Floor framing = 1320 sf @ $5.00/sf            $6600

                           Millwork


                                                          Kitchenette (1)                               $1200

                                                          Counters (2)                                   $800


                                                          Vanities (4)                                  $1500

                                                          Shelving/rod                                   $200




                                                                         Wood and Plastics            $11800