234 The Complete DESIGN BUILDER
l�L CONSTRUCTION
YOUR CO NPLET E DESJG N-8UJLDER
PROJECT : ACME MANUFACTURING BUDGfT fHTIIMTf
Division Heading/Phase Quantity/Unit Cost Cost
5000 Metals
Miscellaneous
Stairs = 2x18R=36 risers @ $250 $8000
Bollards (4) $1000
Ladder (1) $800
Metals $68600
6000 Wood and Plastics
Rough carpentry
Roof parapet = 240 lf @ $6.00 $1500
Floor framing = 1320 sf @ $5.00/sf $6600
Millwork
Kitchenette (1) $1200
Counters (2) $800
Vanities (4) $1500
Shelving/rod $200
Wood and Plastics $11800