Page 260 - TCDB combined Book
P. 260
Chapter 4 ESTIMATING 237
l�L CONSTRUCTION
YOUR CO NPLET E DESJG N-8UJLDER
PROJECT : ACME MANUFACTURING BUDGfH f HI/MHf
Division Heading/Phase Quantity/Unit Cost Cost
10000 Specialties
Washroom Accessories Purchase $3000
Install $1800
Specialties $4800
13000 Special Construction
Metal Building System Beam/Column structure c/w wall
roof systems 100x150x24 = $135000
15000 sf @ $10/sf
Wall liner @ interior x 10320 sf $10300
@ $1.00/sf
3-5/8”steel stud/sheathing
backup x 165 lf x 10 ft. @ $24/lf $4000
Gutters and downspouts $3000
Building System $45000
erection/installation 15000 sf @
$3.00/sf
Special Construction $197300