fSfi!Mff Project: ACME Manufacturing
Division Heading/Phase Quantity Unit Cost
1000 GENERAL
REQUIREMENTS
Design Fees
geo-technical Soil investigation/report ls $3500
structural Foundations/structural/masonry ls 8000
civil/services Site services/drainage ls 3500
architectural Preliminary/ drawings/specifications ls 20000
mechanical HVAC/Plumbing ls 6000
electrical Service /lighting/ distribution ls 4000
testing /inspection Soils/concrete/roofing/structural/asphalt ls 5000
Professional Fees
payment certifier 5 progress claims @ $300.ea. $/ea. 1500
Financials
workers compensation uninsured subtrade workers 10% x $25000. %/$ 2500
Miscellaneous
as-builts Drawings ls 300
operating manuals M/E n/c 0
reproduction Drawings/specs./minutes/schedule ls 500
photography 5 mths. @ $100/mth. $/mth. 500
shop drawings Printing/distribution ls 800
tools ls ls 800
rentals ls ls 1200