Page 267 - TCDB combined Book
P. 267

244                       The Complete DESIGN BUILDER



                                                                             itL   CONSTRUCTION
                                                                              YOuR   CO NPLET E  DESIG  N-8UILDER

                           fSfi!Mff                                       Project:   ACME Manufacturing



               Division      Heading/Phase                        Quantity                  Unit      Cost

               2000      SITE WORK


                         Site Improvements

                             asphalt/concrete paving  1700sy x 4” @$10./sy +2300sy x 3”@ $8/sy.   $/sy   $35400
                                    pavement base   2000 T @ $7./T                           $/T        14000
                                pavement mark/seal   34 spaces @ $25./ea.                    $/ea.        900
                           concrete curbs enclosures   1300 lf @ $8./lf                      $/lf       10400
                                     out buildings   refuse container enclosure               ls         3000
                                import/reuse topsoil   )
                                        plantings   )
                                   seeding/sodding   ) landscaping allowance                allow       15000
                                      trees/shrubs   )
                                        sidewalks   600 sf @ $3./sf                          $/sf        1800
                                     final grading   350 T @ $2.50/T                         $/T          900




               3000      CONCRETE


                         Foundations

                                     strip footings  525 lf @ $6.30/lf conc. + $/2.70lf
                                                 form/place/strip                            $/lf        4700
                                     mat footings  441 sf @ $4.25/sf conc.+ $2.75/sf
                                                 form/place/strip                            $/lf        3100
                                                 600 lf @ $12./lf conc. + $20./lf form/place/strip      19200
                                           walls                                             $/lf
                                            piers   36 @ $30./ea. conc. + $50./ea. form/place/strip   $/ea.   2900

                         Slabs

                                         on deck  3500 sf @ $1./sf conc. + $.75/sf form/place/finish   $/sf   6100
                                         on grade   18500sf @ $1.65/sf conc.+$.60/sf  place/finish   $/sf   41625
                                           sealer   22000 sf @ $.05/sf                       $/sf        1100
                                         sawcuts   1800 lf @ $.50/lf                          $lf         900
                                      thickenings   8 cy  4000 psi conc. @ $100/cy           $/cy         800
                                        hardener  15000 sf @ $.15/sf                         $/sf        2300
   262   263   264   265   266   267   268   269   270   271   272