fSfi!Mff Project: ACME Manufacturing
Division Heading/Phase Quantity Unit Cost
2000 SITE WORK
Site Improvements
asphalt/concrete paving 1700sy x 4” @$10./sy +2300sy x 3”@ $8/sy. $/sy $35400
pavement base 2000 T @ $7./T $/T 14000
pavement mark/seal 34 spaces @ $25./ea. $/ea. 900
concrete curbs enclosures 1300 lf @ $8./lf $/lf 10400
out buildings refuse container enclosure ls 3000
import/reuse topsoil )
plantings )
seeding/sodding ) landscaping allowance allow 15000
trees/shrubs )
sidewalks 600 sf @ $3./sf $/sf 1800
final grading 350 T @ $2.50/T $/T 900
3000 CONCRETE
Foundations
strip footings 525 lf @ $6.30/lf conc. + $/2.70lf
form/place/strip $/lf 4700
mat footings 441 sf @ $4.25/sf conc.+ $2.75/sf
form/place/strip $/lf 3100
600 lf @ $12./lf conc. + $20./lf form/place/strip 19200
walls $/lf
piers 36 @ $30./ea. conc. + $50./ea. form/place/strip $/ea. 2900
Slabs
on deck 3500 sf @ $1./sf conc. + $.75/sf form/place/finish $/sf 6100
on grade 18500sf @ $1.65/sf conc.+$.60/sf place/finish $/sf 41625
sealer 22000 sf @ $.05/sf $/sf 1100
sawcuts 1800 lf @ $.50/lf $lf 900
thickenings 8 cy 4000 psi conc. @ $100/cy $/cy 800
hardener 15000 sf @ $.15/sf $/sf 2300