fSfi!Mff Project: ACME Manufacturing
Division Heading/Phase Quantity Unit Cost
7000 THERMAL/MOISTURE
PROTECTION
Insulation
foundation/rigid 2” SM x 1060 sf @ $1.5./sf $/sf $1600
walls/ batts R20 batts x 5540 sf @ $.65/sf 1” $/sf 4790
walls/ rigid x 1800 sf @ $.75./sf included $/sf 1350
wall vapor barrier above $/sf 0
acoustical demising/private off. X 4000 sf @ $.55/sf $/sf 2200
blanket fiberglass wall/roof R20 x 24120 sf @ $.80./sf $/sf 19300
Roofing
built up roofing Subcontractor firm price ls 20000
curbs allow for 4 @ $125/ea. $/ea. 500
gutters/downspouts 300 lf @ $12./lf $/lf 3600
Siding
pre-finished metal At office-10000 series x 2400 sf @ $ 4./sf $/sf 9600
fascia At office x 200 lf @ $4.50/lf $/lf 900
Caulking
windows/doors )
M/E openings )
siding ) subcontractor firm price ls 1200
roofing )
fascia )