250 The Complete DESIGN BUILDER
l�L CONSTRUCTION
YOUR CO NPLET E DESJG N-8UJLDER
fSfi!Mff Project: ACME Manufacturing
Division Heading/Phase Quantity Unit Cost
9000 FINISHES
Metal framing 3-5/8” s.s. x 8.0 ft. x 600 lf @ $10./lf $/lf $6000
6” s.s. x 10.0 ft. x 660 lf @ $14./lf $/lf 9240
¾” ceiling. furring x 1320 sf @ $.75/sf $/sf 990
Gypsum board ½” std. on steel stud x 12880 sf @ $.85/sf $/sf 10950
5/8” FC on steel stud x 4720 sf @ $.95/sf $/sf 4485
Ceilings 5/8” FC on clg. furring x 1520sf @ $1./sf $/sf 1520
susp. ‘T’ bar lay in tile x 6800sf @ $2.25/sf $/sf 15300
Flooring Purchase allowance only allow 16000
Installation only 880 sy @ avg.$3./sy ls 2640
Painting Subcontractor firm price ls 10000
10000 SPECIALTIES
Compartments/Cubicles
toilet partitions Pre-finished std. Units x 7 @ $500./ea. $/ea. 3500
screens Pre-finished std. Units x 3 @ $250./ea. $/ea 750
Washroom Accessories
allowance Purchase allowance only allow 3000
Installation only ls 400