Chapter   4    ESTIMATING           245



                                                                            l�L   CONSTRUCTION

                                                                            YOUR   CO NPLET E  DESJG  N-8UJLDER

                         fSfi!Mff                                        Project:   ACME Manufacturing


               Division        Heading/Phase                        Quantity                Unit     Cost

               3000      CONCRETE


                         Reinforcement

                                                rebar  8T @ $800./T                         $/T         $6400
                                     welded wire mesh   22000 sf @ $.30/sf                  $sf          6600

                         Accessories

                                        expansion joint  840 lf @ $1./lf                    $/lf          800
                                             bulkhead   70lf @ $7.lf/conc.+$5./lf form/place strip   $/lf   900
                                        anchors/inserts   36 sets of anc bolts @ $25./ea.   $/ea.         900
                                        concrete pump   upper floor slab x 8h @ $150/h      $/h          1200

               4000      MASONRY

                         Unit Masonry


                                     load bearing units  1700-8”@$2.50/ea. matl.+ $3./ea. labor   $/ea.   9350
                              exposed architectural units   2000-4”@$3.50/ea. matl. + $3.50./ea. lab.   $/ea.   14000

                         Brick


                                          exterior face  10000 units@ $550/M matl.+$1200/M lab.   $/M   17500

                         Accessories


                                                rebar  1600 lbs. @ $.40/lb.                 $/lb.         640
                                              blok-lok   2400 lf @ $35./lf                  $/lf          840
                                               sealer   3000 sf @ $.20/sf                   $/sf          600
                                           concrete fill   10 cy @ $100./cy                 $/cy        $1000
                                             brick ties   1700 sf @ 8/sf = 225 @ $1./ea.    $/ea.         225