Chapter 4 ESTIMATING 247
l�L CONSTRUCTION
YOUR CO NPLET E DESJG N-8UJLDER
fSfi!Mff Project: ACME Manufacturing
Division Heading/Phase Quantity Unit Cost
6000 WOOD and PLASTICS
Rough Carpentry
floor framing/sheathing 1320 sf @ $3/sf matl.+ $1.50/sf lab. $/sf $5940
roof parapet 240 lf @ $4./lf matl.+$2./lf lab. $/lf 1500
blocking Ext.door/window/openings x 40@$10/ea. $/ea. 400
backing Wall mounted items ls 300
Finish Carpentry
stairs To mezz. 3.0 ft. wide x 14 risers@$35/R $/R 490
railings At mezz. X 144 lf @ $3/lf $/lf 435
handrail For steel stairs 36R $8/R x 2 $/R 575
closet shelving/rods allow ls 250
fasteners/anchors allow ls 150
Millwork
upper/lower cabinets 8.0 ft. kitchenette @ $125./lf $/lf 1000
vanity tops total 26.0 lf @ $60./lf $/lf 1560
counters total 14.0 lf @ $45./lf $/lf 630
fasteners/anchors allow ls 100