Division Heading/Phase Quantity Unit Cost
5000 METALS
Structural Steel
beam/column-floor/roof framing )21 T@ $1300/T fab.+$700/T erect $/T $42000
floor/roof open web joists )
roof deck 3500 sf @ $1.50/sf $/sf 5250
floor pan 3500 sf @ $1./sf $/sf 3500
anchor bolts 18 units @$6.50/ea. $/ea. 120
Miscellaneous Metals
stairs ) firm subcontractor pricing ls 7000
railings )
handrail )
ladders one unit ls 600
bollards 4 units @ $200/ea. $/ea 800
edge angles mezzanine x 144 lf @ $4./lf $/lf 600