                          fSfi!Mff                                  Project:   ACME Manufacturing



               Division          Heading/Phase                      Quantity             Unit       Cost

               5000      METALS


                         Structural Steel

                              beam/column-floor/roof framing  )21 T@ $1300/T fab.+$700/T erect   $/T   $42000
                                   floor/roof open web joists  )
                                                roof deck  3500 sf @  $1.50/sf            $/sf           5250
                                                floor pan   3500 sf @ $1./sf              $/sf           3500
                                              anchor bolts   18 units @$6.50/ea.         $/ea.            120









                         Miscellaneous Metals

                                                   stairs  )  firm subcontractor pricing   ls            7000
                                                  railings  )
                                                 handrail  )
                                                  ladders   one unit                       ls             600
                                                 bollards   4 units @ $200/ea.            $/ea            800
                                              edge angles   mezzanine x 144 lf @ $4./lf   $/lf            600