Once the Asia Pacific dimensions are registered then the existing licence will be cancelled,
from that point onwards the factory will not be able to produce standard easy on dimension
product, for the local market in Thailand. Products for export will remain unaffected and
separate product licences will cover these.
Fiesta (Asia Pacific easy on coloured and flavoured) Project Number 446
Project Fiesta is to be registered according to ISO 4074:2002.
Cambridge are currently testing 3 batches each of the green kiwi and red strawberry
together with 1 batch each of the yellow banana and orange tangerine. The 3 month data
should be available by mid-May.
The Thai FDA requires an additional 2 batches of the banana and tangerine variants and
these will be prepared by 15** March 2006 and the stability testing will be undertaken in
Thailand.
Action: Surakait to ensure additional batches are prepared and tested
The launch dates for the local market and for export are expected to be November 2006
Action: Surakait to revise the T&E to include the additional batches and confirm
launch dates
The current status of the artwork was discussed.
Action: Tanyalak to confirm status of artwork.
Action: Surakait to forward a copy of the validation report to Andrew Brownhill
Berlin (standard easy on coloured and flavoured) Project Number 447
Surakait confirmed that all of the stability testing associated with Project Berlin will be
undertaken in Thailand.
It was confirmed that Project Berlin will be registered according to the requirements of ISO
4074:2002 with a dispatch to market November 2006. New ovens are currently awaited in
Thailand: these are expected to arrive in May.
Cambridge requested that additional condoms be sent to the UK to undertake burst testing
after 3 months at 30’C. It was noted that this is not a requirement of ISO 4074:2002 but v\^s
for information purposes only.
Action: Surakait to arrange to send 500 pieces of each of the three batches of each
colour and flavour (a total of 12 batches).
The current status of the artwork for Berlin was discussed.
Action: Tanyalak to check artwork status. It was stated that the artwork needs to be in
place before June.