H10 Patent glazing

DESIGN/ PERFORMANCE REQUIREMENTS

211 DESIGN
      • Standard: inverted bar with box section.
          - Sloping and vertical patent glazing to BS 5516-1.
          - Access and openings in accordance with BS 8213-1.
      • Detailed design of patent glazing system: Complete and submit before
          commencement of fabrication.
      • Related works: Coordinate with supporting structure and interfaces in detailed
          design.

311 REQUIREMENTS GENERALLY
      • Extent of compliance: Entire patent glazing assembly, including flashings and
          junctions with adjacent parts of the building.
      • Deflections and other movements: Make full allowance.

361 WATER PENETRATION
      • Requirement: Under site exposure conditions, water must not penetrate onto
          internal surfaces or into cavities not designed to be wetted.

401 THERMAL SAFETY
      • Glazing panes/ units: Must have adequate resistance to thermal stress generated
          by orientation, shading, solar control and construction.

421 SECURITY
      • Fixings to patent glazing bars caps/ wings: Secured to prevent unauthorized
          removal. Submit proposals.

474! BREEAM PERFORMANCE REQUIREMENTS

475 DAYLIGHT PERFORMANCE
      • Daylight calculations: In accordance with BS 8206-2, CIBSE 'Lighting guide LG10'
          and BRE 'Site layout guide'.
      • BREEAM requirements:
          - Submit the following: Daylight performance schedule and Design plans for each
             floor in the building with each room/ area labelled for use.
          - Calculations showing: Average daylight factor expressed as a percentage for
             each room/ area.

480 VIEW OUT
      • Glazed areas/ opening sizes and position: Designed to meet BREEAM 'View out'
          criteria for relevant building type.
      • Submit design plan and elevation drawings showing the following:
          - All BREEAM defined 'relevant areas' dependant on building type and room
             depths.
          - Actual or notional workstation/ desk layouts.
          - Glazed/ open areas.
      • Submit site plan showing: Building location and proximity to external obstructions.