850 ROOF SLOPE TERMINALS
      • Ventilator tiles: site specific.
          - Manufacturer: Contractor's choice.
             Product reference: Contractor's choice.
             Connect to site specific.

          VERTICAL TILING EDGES/ JUNCTIONS

910 BOTTOM EDGES
      • Tiling substrate work: Fix timber tilting fillet to support bottom course of tiles in
          correct vertical plane. Fix flashing to tilting fillet.
      • Underlay: Dress over flashing.
      • Undercourse and bottom course tiles: Fix with tails neatly aligned.

920 TOP EDGES
      • Top course tiles: Fix under abutment and make weathertight with flashings dressed
          down not less than 150 mm.

930 SIDE ABUTMENTS
      • Tiling substrate work: Chase abutment wall and insert stepped flashing.
          - Flashing: Return not less than 75 mm behind tiling, overlapping underlay and
             battens. Turn back to form a vertical welt.
      • Abutment tiles: Cut and fix neatly.

940 ANGLES WITH ANGLE TILES
      • Angle tiles (purpose made): Fix right and left hand in alternate courses to break
          bond.
      • Adjacent tiles: Cut and fix neatly.

950 ANGLES WITH SOAKERS
      • Angle tiles: Cut tile and a half tiles and fix to form a straight, close mitred junction.
      • Soakers: Interleave with angle tiles. Fix by nailing to battens at top edge.

960 JUNCTIONS WITH ROOF VERGES
      • Tiling substrate work: Fix additional tiling batten parallel to and below verges.
      • Course end tiles: 'Winchester cut' tile and a half tiles to angle of verge rake. Fix to
          additional tiling batten with cut edge parallel to and below verge.

RotF generic (intermediate) NBS 2014  6118-AEW-XX-XX-NBS-A-01