715 LAYING FLAG AND SLAB PAVING - MORTAR LAYING COURSE AND JOINTING
      • Standard generally: In accordance with BS 7533-4.
      • Flag installation and cutting: To Interpave 'Concrete flag paving'.
      • Laying course:
          - Nominal thickness: site specific.
      • Laying and jointing: site specific.
      • Joint width (nominal): 10 mm.

725 LAYING RIGID BRICK PAVING
      • Standard generally: In accordance with Brick Development Association Design
          Note 8.
      • Bedding and jointing method: Simultaneous bedding and jointing with stiff plastic
          mortar.
      • Cement slurry: Apply thin slurry (1-3 mm) of neat cement or 1:1 cement:soft sand
          over the freshly laid mortar bed immediately prior to laying bricks.
      • Laying: Wet bricks as necessary (but do not soak), butter joint faces and press
          down firmly to give a level surface with 10 mm regular joints.
      • Nominal thickness of bed: site specific.
      • Joint profile: Bucket handle.

750 LAYING NATURAL STONE COBBLE PAVING
      • Bedding, laying, jointing and completion: In accordance with BS 7533-7 and -10.

760 LAYING PRECAST CONCRETE AND GRAVEL PAVING
      • Laying: Tamp down into lightly compacted laying course.
          - Nominal thickness of laying course after compaction: site specific.
      • Filling: Allow to settle and refill level with surface.

785 TOOLED JOINTS IN MORTAR BEDDED UNITS
      • Joints: Completely filled with bedding mortar as work proceeds.
          - Joint width: 6-10 mm.
          - Finish: Neat flush profile.

800 APPLYING SEALANT/ STABILIZER TO BLOCKS AND SETTS
      • Surface preparation: Ensure sand joints are completely dry and free from
          contamination and Sweep clear of loose sand before sealing.
      • Sealer/ stabilizer: Contractor's choice.
          - Application: To dry paving.
             Method: To manufacturer's recommendations.
             Number of coats: site specific.
             Coverage: site specific.

          COMPLETION

915 COMPLETION OF PAVING WITH DRY SAND OR FINE AGGREGATE FILLED JOINTS
      • Sand dressing: Leave a thin layer of dry jointing sand over the paving, sweep clean
          before practical completion.
      • Final compaction of the surface course: In accordance with BS 7533-3.
      • Vacuum cleaning machines: Not allowed.