Page 17 - LINK - HSE Client duties - CDM 2015-clients-interactive
P. 17

Annex A  CDM duty holders and their roles summarised





                CDM duty holders* – who are they?  Summary of role/main duties                    CDM duty holders* – who are they?  Summary of role/main duties
                Principal contractors          Plan, manage, monitor and co-ordinate              Workers                       They must:
                Contractors appointed by the client   health and safety in the construction       The people who work for or under   •  be consulted about matters which
                to co-ordinate the construction   phase of a project. This includes:              the control of contractors on a   affect their health, safety and welfare
                phase of a project where it involves   •  liaising with the client and principal   construction site.           •  take care of their own health and
                more than one contractor.       designer                                                                          safety and that of others who may be
                                               •  preparing the construction phase                                                affected by their actions
                                                plan                                                                            •  report anything they see which is
                                               •  organising co-operation between                                                 likely to endanger either their own or
                                                contractors and co-ordinating their                                               others’ health and safety
                                                work.                                                                           •  co-operate with their employer,
                                               Ensure that:                                                                       fellow workers, contractors and
                                               •  suitable site inductions are provided                                           other duty holders.
                                               •  reasonable steps are taken to                  * Organisations or individuals can carry out the role of more than one duty holder, provided they have
                                                prevent unauthorised access                      the skills, knowledge, experience and (if an organisation) the organisational capability necessary to
                                               •  workers are consulted and engaged              carry out those roles in a way that secures health and safety.
                                                in securing their health and safety
                                               •  welfare facilities are provided.
                Contractors                    Plan, manage and monitor construction
                Those who do the actual        work under their control so that it is
                construction work. They can be   carried out without risks to health and
                either an individual or a company.  safety.
                                               For projects involving more than one
                                               contractor, co-ordinate their activities
                                               with others in the project team – in
                                               particular, comply with directions given
                                               to them by the principal designer or
                                               principal contractor.
                                               For single-contractor projects, prepare
                                               a construction phase plan.







         Industry guidance for clients                                                                                                                         17