Page 11 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 11

RAM                   Internal PM              External PM                    QS                    Architect                  Format


                 Site identified


             RAM agrees site with LP&P


            RAM completes draft Investment                     Ex.PM instructs the Architect and                    Architect undertakes Stage 1
              Appraisal [IA] and instructs                       QS to proceed with Stage 1                             feasibility study
                Ex.PM to new site
                                                                 Ex.PM sets project plan and
                                                                    issues to team


            Project plan received from Ex.PM  Project plan received from Ex.PM           Project plan received from Ex.PM  Project plan received from Ex.PM  Project plan received from Ex.PM


                                                                                                                     Architect issues Stage 1
                                                                                                                    feasibility drawings to Ex.PM



                                                                 Stage 1 feasibility drawings
                                                                      received

                                                                 Ex.PM reviews and obtains
                                                                agreement from Logistics Team
                                                                                                                                            Dialogue between
                                                                                                                                            Asset Team and
                                                                                                                                           Architect until Stage
                                                                                                                                           1 feasibility and Asset
                                                                                                                                           Plan are co-ordinated
                                                                      Updates                 YES                    Architect updates Stage 1
                                                                      required?                                        feasibility drawings
                                                                       NO
                                                                 Pre Construction Support                                                   Format Team produce Asset Plan
                                                                   Document 00 & 01

                                                                                                                     Architect issues the final   Asset Plan issued to Ex.PM and
                                                                                                                                                                   NOT AGREED
                                                                                                                   co-ordinated Stage 1 feasibility   Governance
                                                                                                                         to Ex.PM


            Stage 1 Feasibility  drawings and                  Stage 1 Feasibility drawings and                                                    Governance
            Asset Plan received from Ex.PM                      Asset Plan received and issued                                                     Approval?
                                                                      to RAM

              RAM to review and obtain
               agreement from RLA                                                                                                                  AGREED
                  AGREED

              Zonal analysis undertaken                           Review and update Pre
               and issued to Ex.PM                             Construction Support Document
                                                                02, 03 and 04 & issue project
                                                                  information to the QS


                                                                                          CV1 cost document developed


                                                                 Scheme Approval 1 Pack   Scheme Approval 1 Pack
                                                                  CV1, Stage 1 Feasibility   CV1, Stage 1 Feasibility drawings,
                                                                drawings, Asset Plan & Zonal   Asset Plan & Zonal issued to
                                                                      received                  Ex. PM




                                                                      Review
                                                                    Scheme Approval           YES
                                                                      1 Pack.
                                                                     Are updates
                                                                      required?
                                                                       NO

                                                                 Scheme Approval 1 Pack
                                                               CV1, Stage 1 Feasibility drawings,
                                                               Asset Plan & Zonal submitted for
                                                                    scheme approval


                                       Attend Scheme Approval 1   Attend Scheme Approval 1   Attend Scheme Approval 1
                                            Meeting                   Meeting                   Meeting

             Scheme aborted or   REJECTED  Project reviewed at Scheme   APPROVED
            reworked at a later date     Approval 1 Meeting
                                                                                           Issue Approved Stage 1 Pack
                                       Internal PM issues Scheme                          & CV1 Investment Appraisal
                                      Approval meeting minutes to the                     Summary to RAM during the
                                             team                                               meeting


              Scheme Approval Meeting                            Scheme Approval Meeting   Scheme Approval Meeting                            Scheme Approval Meeting
                minutes received                                    minutes received         minutes received                                    minutes received
        REJECTED




                 RAM to review
                  and obtain
                 approval from
                    FPB



                 APPROVED


                 FPB Approval                                      Proceed to Stage 2
   6   7   8   9   10   11   12   13   14   15   16