Page 49 - PA BOOKLET 2022
P. 49
B Works in Progress (Rs. In '000s)
Year of Name of work PH Cost TDC Remarks
sanc
19-20 Provn. of monumental flag at Manchiryal station. PA 1080 Dec'22 Work completed
(Column errection work completed.
construction of one additional FOB at Manchiryal
18-19 PA 32303 Jan'23 Launching of girder planned in
stations.MCI
November 2022.
SC Division MCI Improvements to KZJ end Goods loading
21-22 PA 19040 Mar'23 Work is in progress.
Platform
Improvements to Goods PF from FOB to BPQ end at MCI
22-23 PA 24747 Mar'23 Tender will be opening on 14.11.2022
and Provision of cover shed at SC VP siding.
22-23 Installation of 32 OSOP stalls at 23 stations over SC Division PA 812 Mar'23 Work is in progress.
PA total 77982
47
Summary(fig in 000's)
PH Completed In progress Total
SW 4725 0 4725
PA 20274 77982 98256
G Total 24999 77982 102981