Page 62 - PA BOOKLET 2022
P. 62
RECHINI ROAD Category-NSG-6
A Works completed in the last Five years (Rs. In '000s)
Sl.No Name of work PH 2017-18 2018-19 2019-20 2020-21 2021-22
Rechni Road-Provision of S&T and OHE arrangements for
1 proposed extension of shunting neck towards Kazipet TF 2995
end.
TF total 2995
Improvements to Balconies and Sewerage system to staff
2 SW 825
quarters in KZJ-BPQ section.
SW Total 825
B Works in Progress (Rs. In '000s)
60
Year of Remarks
sanc Name of work PH Cost TDC
Work is executing by Construction
18-19 Provision of FOBs at RECH station. PA 19767 --
Organisation with Third line Funds.
PA total 19767
Summary (fig in 000)
PH Completed In progress Total
TF 2995 0 2995
SW 825 0 825
PA 0 19767 19767
G Total 2995 20592 23587