Page 430 - Mines Facilities Plan
P. 430

ve (5)    ve









                                 EXISTING CAMPUS ELECTRICAL SUMMARY





















                                              CAPACITY CAMPUS PEAK DEMAND AND XCEL ENERGY  Based on the 600A primary meter rating, the maximum capacity of Xcel  Energy’s service to Mines is 13.7 MVA, and the campus peak electrical  demand for the past year was 6.4 MW. Based on that demand and assuming  a 0.87 power factor, Xcel Energy is able to supply up to an additional 5.5 MW  of load from the existing medium voltage service. CAMPUS PEAK DEMAND AND ISOC GENERATOR   PLANT As part o








                                                               installed as part of an Interruptible Service Option Credit (ISOC), which allows
                                                                                                   (east of Maple Street and west of Washington Street between 18th Street and
                                           UTILITY SERVICE AND CAMPUS MEDIUM VOLTAGE
                                                                                              2A/2B primarily serves campus buildings south of 17th Street to 19th Street.
                                                                               loops (Loop 1 and Loop 2). The loops extend through campus from the new
                                                                  Xcel Energy to shed the Mines load during periods of peak demand. During
                                                                                    of the Wright Wellness Center. Loop 1 and Loop 2 each include A & B sides
                                                 The Mines campus is fed by an Xcel Energy electrical system from Lookout
                                                    Substation at 13.2 kV through an 800A substation circuit breaker to a 600A
                                                                            The campus medium voltage electrical distribution system includes two (2)
                                                             switchgear that were installed in 2017/2018. In 2018 a generator plant was
                                                       rated Xcel Energy primary meter. From the primary meter, medium voltage
                                                                                                 Loop 2A/2B will serve the future campus expansion to the east expansion
                                                                                 S&C Vista 624 switchgear installed in 2017/2018 that is on the north side
                                                                     these times, the campus is served by Mines’ ISOC generator plant and is
                                                          is routed through to two (2) Mines-owned 600A, 15.5 rated kV S&C Vista
                                                                                           Loop 1A/1B primarily serves campus buildings north of 17th Street. Loop
                                                                                       originating from four (4) 400A circuit breakers in the 624 switchgear.
                                                                                                                       Colorado School of Mines Facilities Master Plan


















                          8.0                 LOOPS                     disconnected from the Xcel Energy service.  17th Street) as proposed by the Facilities Master Plan.  424
   425   426   427   428   429   430   431   432   433   434   435