Page 434 - Mines Facilities Plan
P. 434

PROPOSED CAMPUS ELECTRICAL SUMMARY
















                                          the existing campus demand. Using historical power density data from Mines and other sources, SBEC  anticipates approximately 6.0 MW of load being added during the course  of the master plan. A summary of the new loads is included in the following   table.  NOTES: The estimated demand for the Washington/18th Street Parking Structure includes   1.   Chiller Plant 8 (CP8). 2. Buildings with “Mines Park” in the name will be on the west side of H
















                                                                                         310.60(C)(78), using the 90°C column. If the conductors and terminations are
                                                 loads be taken at 125 percent. However, in the past Mines has requested and
                                                                   The electrical calculations assume that the power factor during peak demand
                                                       with respect to the campus medium voltage system. For the purposes of this
                                                                             The w/sf that was utilized in SBEC calculations is based upon historical data
                                                                                      The ampacity of medium voltage feeders was derived from 2017 NEC Table
                                                                                                             buildings, most of the associated electrical load is expected to be additive to
                                                         master plan, it is assumed that a similar approach would be taken for future
                                                                               provided by Mines as well as SBEC’s past experience. A 15 percent safety
                                                                                                 FACILITIES MASTER PLAN AND PROJECTED LOAD
                                                            buildings and existing loads are calculated at 100 percent rather than 125
                                                    received permission from the State to deviate from NEC load calculations
                                                                                                           (2) new chiller plants. While some of these buildings will displace existing
                                              When calculating the load within buildings, the NEC requires that existing
                                                                                                        seventeen (17) new buildings, three (3) new parking structures, and two
                                                                      is 0.87. This assumption is based on information provided by Mines and
                                           BACKGROUND OF SBEC CALCULATIONS
                                                                                                                      











                                                                         SBEC’s past experience.  factor was then added to new loads. rated for 105°C, then the conductors would have a higher ampacity. The Facilities Master Plan recommends constructing approximately   Colorado School of Mines Facilities Master Plan






                  9.0                                          percent.                                               428
   429   430   431   432   433   434   435   436   437   438   439