Page 439 - Mines Facilities Plan
P. 439
Load by Neighborhood – Central Campus, and Chilled Water: Estimated Load
plants as they are looped together. CP8 is only intended to serve as a backup
changes as a part of this master plan. Refer to Chilled Water: Estimated Load
433
CP8) in order to serve all of the Research Park neighborhood. More in depth
investigation is required to design and control the two (and eventually three)
Chilled Water: Chiller Plant Capacities and Loads, Chilled Water: Estimated
this master plan are constructed, the CP6 and CP7 loop will have very little
Estimated Load by Neighborhood – West Campus for a breakdown of CP6
redundancy and no backup which is why CP8 will be constructed. Refer to
redundancy to the looped CP6 and CP7. CP5 is not anticipated to see any
to this plant are Spruce Hall (Residence Hall VI) and the Frontiers Building
The master plan plans to connect and loop CP6 with CP7 (and eventually
(located within the Research Park neighborhood). All of the buildings that
anticipated to receive a new chiller plant, Chiller Plant 8 (CP8) to provide
should one or two chillers go down at any time. Once all the buildings in
Research Park houses one (1) chiller plant, Chiller Plant 5 (CP5) and is
additions would remain as stand-alone cooling. Refer to Chilled Water:
currently have stand-alone cooling systems and anticipated to receive
Appendix 2: Utilities Master Plan
and what buildings are served by it. by Neighborhood – West Campus for more information. by Neighborhood – Research Park more information.
The Innovation Hub has one building that will be served by CP4 located within
analysis of the assumed diversity and operation of CP4 is recommended prior
Chilled Water: Estimated Load by Neighborhood – Innovation Hub for a list of
direct expansion cooling. An alternative to this approach would be to provide
by Neighborhood – Central Campus for a breakdown of each plant and what
Central Campus. The remaining buildings are proposed to have stand-alone
and Chiller Plant 7 (CP7). Together these chilled water plants can serve the
proposed added construction within this neighborhood. It is anticipated that
building and possibly back feed the General Research Laboratory. Refer to
(Student Innovation Hub). Direct buried distribution chilled water main from
this chiller plant would be provided with the construction of each additional
to adding all anticipated buildings. Refer to Chilled Water: Estimated Load
a small chiller plant to be located within the first building to be constructed
Central Campus houses two (2) chilled water plants, Chiller Plant 4 (CP4)
no modifications will be required in either plant. However, a more detailed
West Campus houses one (1) chilled water plant, Chiller Plant 6 (CP6). It
is anticipated that this plant will have a new chiller installed in 2019. This
addition would allow the plant to provide the necessary cooling for the
RECOMMENDATIONS
CONCLUSIONS AND
all the anticipated new buildings in this neighborhood.
anticipated new construction. The first two buildings anticipated to be added
buildings are served by them.
11.0 COOLING