Page 440 - Mines Facilities Plan
P. 440

possible to delay installation of PowerBlock #4 until construction of Research
                                                                               Building 1 in 2023. At completion of the master plan, the campus load (12.4
                                                                                  MW) is anticipated to exceed the capacity of the ISOC generator plant with
                                          either variable refrigerant flow or ground source heat pumps as their main
                                                              recommends installation of two additional gensets in PowerBlock #1 prior
                                             source of heating. The other proposed buildings would receive dedicated
                                                         The existing peak demand (6.4 MW) for the campus exceeds the current
                                                                 to next year’s peak demand, which typically occurs between August and
                                                                       additional gensets would need to be installed prior to bringing additional
                                                                          buildings online. If a load shedding strategy is implemented, it may be
                                                                    September. It is anticipated that PowerBlock #4 with at least three (3)
                                                            capacity of the ISOC generator plant (6.2 MW). As a result, SBEC









                                                                                       PowerBlock #4 at its full capacity of five (5) gensets (total of 10.1 MW of  capacity). As a result, it will be necessary to implement a load shedding  strategy to allow implementation of the master plan while remaining within  the capacity of the ISOC generator plant. Mines will have additional historical  electrical peak demand data at that time, which can be reviewed against the  Based on Mines-S




                                                                                                   generator plant total available capacity.  shedding loads, which are listed below:


                                               boilers for heating.  ELECTRICAL                                  










                                              Existing buildings to be renovated within Mines Park are anticipated to remain
                                                      source heat pumps. Refer to Chilled Water: Estimated Load by Neighborhood
                                                                                            Steam: Anticipated Campus Load Summary for a breakdown of buildings and
                                                 as stand-alone direct expansion cooling. New construction within Mines Park
                                                                     and beyond those identified in the Campus Infrastructure Upgrade Project in
                                                                                provide the heating for all the proposed buildings within the master plan that
                                                                  The steam distribution piping requires a couple upgrades in pipe size above
                                                                                         all the anticipated condensate load of the proposed new buildings. Refer to
                                                                        order to provide heating to the proposed new buildings throughout campus
                                                   is expected to be provided with variable refrigerant flow systems or ground
                                                                                   are anticipated to be connected to the heating plant. The heating plant will
                                                                                      need to receive two new condensate pumps in order to receive and pump
                                                                           and maintain a fluid velocity below 140 FPS as recommended by Spirax
                                                                              Sarco. However, once these upgrades are in place, it should be able to
                                                                                                  The new buildings in the Innovation Hub and on South Campus are
                                                                                                     anticipated to receive dedicated gas fired condensing boilers.
                                                                                                                      
                                          South Campus development will provide its own cooling.



                                                                                                         The existing buildings to be renovated within Mines Park would have gas  fired boilers shared between two buildings. The proposed apartment buildings  within Mines Park would have gas fired boilers for supplemental heat and
                                                                                                                      Colorado School of Mines Facilities Master Plan
                                                         – Mines Park for more information.  HEATING        their associated steam and condensate loads.     434
   435   436   437   438   439   440   441   442   443   444