4"          Wye Strainer              3     pc/s               39,690.00   80%  10%  90%                   35,721.00
      4"          Check Valve               6     pc/s             129,600.00   80%  10%   90%                 116,640.00
      4"          Gate Valve                8     pc/s             168,480.00   80%  10%   90%                 151,632.00
      3"          Gate Valve                2     pc/s               22,950.00   80%  10%  90%                   20,655.00
      4"          Float Valve               3     pc/s             396,900.00   80%  10%   90%                 357,210.00
                  Pressure Gauge            3     pc/s                 1,822.00   80%  10%  90%                    1,639.80
                  Saddle adaptor            24    pc/s             249,480.00   80%  10%   90%                 224,532.00
      SUB TOTAL COST:                                          3,237,523.00                  90%           2,913,770.70



                Item Description                            Amount      Previous   Present   To Date   Amount
      Pump piping                                                  150,000.00   0%  0%     0%                            -
      Setting of Plumbing fixtures                                 545,000.00   55%  35%   90%            190,750.00
      Tapping of Water Meter, Drainage and Sewer Line              350,000.00   70%  20%   90%                 315,000.00
      Vat                                                     1,518,474.60   80%  10%      90%             1,366,627.14
      Hanger, Bracket, Pipe Sleeving, Consumable & Contingency       4,287,052.00   80%  10%  90%            3,858,346.80
      SUB TOTAL COST:                                          6,850,526.60                  81%           5,539,973.94

      TOTAL AMOUNT:                                          26,750,000.00                   89%        23,737,731.13



       Contract Amount                             Php       26,750,000.00
       Percentage of Accomplishment                                         0.89
       Amount of Accomplishment                    Php       23,737,731.13
       Deductions:
       10% Retention                               Php         2,373,773.11
       Pro-rata downpayment  6,687,750 X 89%       Php         5,951,875.00
       Billing No. 1                               Php         4,171,983.50
       Billing No. 2                               Php         1,786,423.33
       Billing No. 3                               Php         1,678,009.56
       Billing No. 4                               Php         1,877,354.34
       Billing No. 5                               Php         3,285,262.98

       Net Amount for Billing No.:006              Php         2,613,049.31