Page 29 - ROYAL VIEW BILLING REQUEST
P. 29
PHASE I & II - 40 out 58 Units COMPLETED
th
(2 nd – 4 floor) – typical floor
CLUSTER CLUST6R CLUSTER CLUSTER CLUSTER CLUSTER 14 & 15
I & 9 2 & 6 3 & 7 4 & 10 5A & 5B
UNIT A UNIT B UNIT A UNIT B UNIT C UNIT D UNIT A UNIT B UNIT C UNIT D UNIT A UNIT B UNIT C UNIT D UNIT A UNIT B UNIT A UNIT B UNIT C UNIT D INSTALLED STATUS
BED ROOM TOILET
• Watercloset (w/ seat & cover 40/58 COMPLETED
• Lavatory w/ pop up drain 40/58 COMPLETED
• Faucet 40/58 COMPLETED
• Shower 40/58 COMPLETED
• Tissue holder 40/58 COMPLETED
• Strainer 40/58 COMPLETED
• Pendent sprinkler 40/58 COMPLETED
• Sidewall sprinkler (door) 40/58 COMPLETED
• Sidewall sprinkler (room) 40/58 COMPLETED
DOOR ROOM
BALCONY SINK
• Faucet 40/58 COMPLETED
• Ptrap 40/58 COMPLETED
• Drain 40/58 COMPLETED
• Strainer 40/58 COMPLETED
BAR SINK
• Faucet 40/58 COMPLETED
• Sink 40/58 COMPLETED
• Ptrap w/ flexible hose 40/58 COMPLETED
• Sidewall sprinkler 40/58 COMPLETED