Page 43 - Bernardon Response to RFP-CRISP Bldg 709
P. 43
www.bernardon.com
■ Visit the site at substantial completion This proposal makes the following Assumptions:
and issue the Certificate of Substantial
Completion. ■ Existing drawings in all disciplines are
available and are accurate.
Our proposal is based upon the construction ■ Demolition drawings will depict areas of
period having a duration of no more than nine demolition with piping to remain being
(9) months. capped. Detailed survey of systems to be
demolished is not included in our proposed
fee.
Additional Services, Exclusions, Assumptions ■ Shell space will not be provided with means
of heating. Design of a temporary heating
Our services are limited to the scope of services system is not included in our proposed fee.
described above. If the scope of the project or ■ A performance specification will be provided
our services changes, we reserve the right to for fire protection and life safety work.
invoice for Additional Services. Examples of ■ Design of all mechanical utilities will extend
Additional Services would include: to five (5) feet outside the building. Design
beyond that point will be provided by others.
■ Making Owner-requested revisions to We have included time to coordinate with the
previously approved drawings. Civil Engineer.
■ Making “value engineering” changes to ■ Design of emergency generator is not
the drawings after receipt of bids. included in our proposed fee.
■ Providing services after a substantial ■ For design of audio/visual, voice/data,
delay in the project schedule. security systems, MEP Engineer will work
with equipment supplier and provide
The following are not included in our scope: performance specification for bidding and
construction. MEP drawings will include
■ Civil engineering, landscape architecture, or locations for outlet box and raceways. We
any site improvements. have not included in our proposed fee for the
■ Geotechnical engineering. services a specialty consultant.
■ Material testing and structural construction ■ Exterior lighting design is limited to building
inspection services. specific exterior lighting. Design of parking
■ Construction cost estimating. lot lighting system is not included in our
■ Audio/visual, voice/data systems, and proposed fee.
equipment.
■ Security. We can begin performing our services upon
■ Interior and exterior signage other than that receipt of written authorization to proceed. This
required by code. proposal is valid for six (6) months. Our form of
■ Selection and documentation of furniture, agreement will be based on the AIA B141 Owner-
fixtures, and equipment (FF&E). Architect Agreement, modified to suit this project.
Enclosed are our Terms and Conditions which are
a part of this proposal.