Schedule
Chestnut Run Innovation & Science 2021 2022
Park Campus Concept Master Plan JUNE JULY AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG
Project Schedule
1 Kick-Off *
6/21
1 Project Initiation
6/21-6/27
2 Conceptual Site Planning
6/28-7/8
Draft Illustrative Site Plan & Engineering
3
Deliverables 7/9-7/15
Finalize Illustrative Site Plan and Engineering
4
Deliverables 7/16-7/20
Begin Test Fits and Concept Design for Building 709 *
5
Renovations 7/21
Shell and Core Documentation for Building 709
6 7/21-9/30
Renovations
7 Bidding for Building 709 Renovations
10/1-10/31
8 Building 709 Construction *
11/1/2021 - 7/29/2022
Contract Document
We can begin performing our services upon receipt of written authorization to proceed. This proposal
is valid for six (6) months. Our form of agreement will be based on the AIA B141 Owner-Architect
Agreement, modified to suit this project. As noted above, reimbursable expenses for such items as
printing, travel and overnight delivery are not included in the professional fees noted above and will be
invoiced at 1.1 times our cost. Enclosed are our Terms and Conditions which are a part of this proposal.
BERNARDON | Response to Request for Proposals | MRA Group
Chestnut Run Innovation & Science Park | Campus Concept Master Plan | June 14, 2021 Page 43