P&H WAS ALMOST BUILT IN “The new facility, set to open early next year at
A DAY! (by Jesse Peltier) 807 W. Harris Road in south Arlington, will house
the company’s manufacturing plant, office and
warehouse operations under one roof.
For those who haven’t seen the construction
progress at the site of the new P&H complex At 173,000 square feet, the new facility will be
lately, this video should bring you right up to more than triple the size of the company’s current
speed :-) distribution facility on West Harris Road and man-
ufacturing facility on Commercial Boulevard.
https://www.facebook.com/phcasters/vid-
eos/212918264093301 Last December, the Arlington City Council ap-
proved a Chapter 380 agreement with P&H Cast-
Over this past weekend, the building site ers in support of the relocation and expansion,
became a new home for P&H, virtually over- which is expected to generate new tax revenue
night! for the City.
Jesse relayed that now that the walls are up, The expansion will also mean new engineering
the weather, which tends to become more and production-related job openings for the com-
erratic as fall arrives, will have less of an im- pany, which currently has 64 employees, Peltier
pact on the construction schedule. said.”
He said, “Completion date range is anticipat- Excerpted from an aritcle by Susan Schrock, City
ed to be mid-to-late January at this point. “ of Arlington’s Office of Communication posted on
June 09, 2021.
2022 is shaping upto be a very memorable
year for P&H.