Subcontractor Management




                       Subcontractor Management


                       Purpose
                       The PM shall approach managing subcontractors based on the following principles:
                          The PM shall be established to effectively support the needs of the subcontractors
                          The  PM  shall  establish  and  clearly  define  effective  channels  of  communications  with  the
                          subcontractors
                          A Statement of Work shall be developed jointly by the PM and CA, with each subcontractor
                           taking responsibility for the deliverables and services outlined in its areas of responsibility
                          The PM shall reinforce all deliverables provided by the subcontractor will be subject to the
                           acceptance of Vysnova and the Government Client.
                          The PM shall monitor and evaluate that subcontractor deliverables ensuring that they meet
                           and/or exceed the requirements of the contract.
                          The PM shall review and approve invoices and shall support Vysnova Accounting in processing
                           invoices and payments for subcontractors.
                          The PM understand all terms and conditions of each subcontract, including but not limited to
                           invoice management, burn rates, and reporting requirements.

                       Identifying and Verifying Subcontractors
                       Post Award, the PM shall follow up with subcontractors and confirm that they can commence
                       performance under Prime Contractor’s direction.
                       The PM shall verify that all subcontractors and consultants are properly licensed and insured in
                       accordance with the terms and conditions of the Prime Contract. The PM shall ensure that the
                       subcontractors take all the required training (e.g. HRPO). PMs will work with the CA to ensure that
                       all  subcontractors  are  verified  in  SAM.gov  to  confirm  that  the  subcontractor  has  not  been
                       debarred by the Federal Government (see SAM Exclusion List in www.SAM.gov).

                       Subcontract Elements
                       Defining Statements of Work or Performance Work Statements
                          Individual Statements of Work (SOW)/Performance Work Statements (PWS) shall be issued
                          with each Task Order issued under IDIQ base vehicle. Otherwise, general subcontracts and
                          Consulting Agreements will contain one specified SOW or PWS, unless additional scopes of
                          work are added through contract modification.
                          PM shall reinforce that the Subcontractor shall only perform work under contract as directed
                          in written Task Orders issued by the CA.
                          The  PM  shall  specify  each  subcontractor’s  deliverables/or  services  and  required  content
                           clearly defined in the proposed Statement of Work or Performance Work Statement in the
                           agreement.
                          All  constraints  imposed  on  the  subcontractor  will  be  clearly  identified  in  the  SOW/PWS,
                           including schedule and budget constraints.
                          The subcontract shall delineate that subcontractor personnel will report to the PM on all
                           technical matters.