5-7 days 4-6 weeks 1-2 weeks 1-2 weeks 3-6 weeks 2-3 weeks
Initial contact from Initial contact from Excavation: The Slab, block wall or The sub-floor, Heating, air condi-
homeowner or first homeowner or first home’s position is poured wall founda- walls, and roof tioning, plumbing
responder. We responder. We staked and prepped tions are prepared structure are built, and electrical are
evaluate, create evaluate, create for the foundation. for the framing and your roof is handled during this
project list, & con- project list, & con- Demolition: the area stage. shingled. Window portion of the time-
tact appropriate tact appropriate of home that dam- and door units are line.
parties for bids. parties for bids. aged is removed installed. Backfilling
and cleaned up. is also completed.
1 week 1 day 3-6 days 2 weeks 1 week 1 week
Inspections to cover This is a day when Insulation is in- Drywall is hung and Carpentry and The home is painted
the initial phases of the customer is given stalled in the walls, finished, and the woodwork is fo- in its entirety.
construction or the opportunity to and drywall is ceilings are insu- cused on during this
restoration. walk-thru their staged in each lated giving a vis- stage. Trims around
home, ask questions, room for future ual effect of the doors and windows
and communicate installation. entire space. are installed.
concerns.
5-6 weeks 1 week 1 week 1 day 1 week Turn Over
From initial order. Plumbing hardware, Carpeting, hard- Customer walks Punch list items the Keys!!
Cabinets are in- switch plates, plug woods, tile and through home and have been com-
stalled in 2 - 4 days covers, light fixtures, other flooring is helps contractor pleted, customer is
from delivery to the air/heat pump unit, installed. create a punch list given final tour of
site. register and return air of final items to be their new/restored
covers and other completed. home.
subcontractor details.