Page 10 - AsianOil Week 47
P. 10

AsianOil                                         OCEANIA                                             AsianOil




























                                                                                       Image: Santos
                           The company said it had already begun work-  and Financial Analysis (IEEFA) financial ana-
                         over activities on existing wells under its current  lyst Bruce Robertson has poured cold water on
                         exploration tenures and was working to secure  those projections. He argued in the run-up to
                         various agreements required before proceeding  the IPC’s approval that Santos could not make
                         to the next phase of development. Santos intends  a profit from Narrabri without selling the gas at
                         to up to 850 wells with eventual output ring-  much higher prices.
                         fenced for the local market.           He said that while the government is cam-
                           Santos has previously said the project could  paigning for Australian gas prices of around
                         deliver 70 PJ (1.82bn cubic metres) per year of  AUD4 ($2.95) per GJ to underwrite a boom in
                         additional gas to the domestic market by 2023.  the domestic manufacturing sector, Narrabri
                         With NSW importing 95% of the gas it needs  production would likely cost around AUD8.50
                         from other states, Narrabri could help to lower  [$6.26] per gigajoule. This, he said, meant “gas
                         the state’s gas bill.                consumers are likely to see higher, not lower gas
                           However, Institute for Energy Economics  prices if the fields are approved”.™




       Chevron restarts Gorgon Train 2 production





        PROJECTS &       CHEVRON has restarted production from  Train 1 has been returned to service. The length
        COMPANIES        Train 2 at its Gorgon LNG terminal in Western  of the shutdowns depends on what is discovered
                         Australia after some delays during the process of  during the inspections and whether any repairs
                         making repairs to propane heat exchangers – or  are necessary.
                         kettles – at the facility.             “Insights gained from Train 2 repairs will
                           Media reported this week that the train had  contribute to more efficient inspections and
                         resumed production. This marks the end of an  potential repairs on Trains 1 and 3, with prepa-
                         outage that started in May when Chevron shut  rations underway for shutting down Train 1 for
                         Train 2 down for scheduled maintenance, sub-  inspections,” Chevron was reported as saying on
                         sequently saying in July it had discovered weld  November 24.
                         quality issues affecting the kettles. The Austral-  The AMWU is reported to have remained
                         ian Manufacturing Workers Union (AMWU)  concerned over safety at Gorgon, calling for
                         said this had resulted in cracks of up to 1 metre  an immediate shutdown of the remaining two
                         long and 30 mm deep, which were found on 8-11  trains for inspections, as well as an independ-
                         kettles on Train 2.                  ent investigation into the repairs carried out on
                           Initially there were concerns that it would be  Train 2. However, Chevron has insisted that the
                         impossible to make repairs to the kettles, and  train is now operating safely.
                         that they would need to be replaced. Chevron   Gorgon has a total capacity of 15.6mn tonnes
                         managed to avoid this, but an initial target of  per year (tpy). The facility includes a carbon
                         restarting Train 2 in September was pushed back  capture and storage (CCS) project, but Chev-
                         to October, and then November. The super-ma-  ron has fought a separate battle to operate it. No
                         jor now has to take Trains 1 and 3 offline to  carbon dioxide (CO2) was stored until August
                         inspect their kettles for similar issues. Train 1 will  2019, more than three years after Gorgon began
                         be taken offline first, with Train 3 following once  exporting LNG.™



       P10                                      www. NEWSBASE .com                      Week 47   26•November•2020
   5   6   7   8   9   10   11   12   13   14   15