Page 4 - AfrElec Week 07 2021
P. 4

AfrElec                                       COMMENTARY                                              AfrElec




       Mozambique LNG project may be





       back on track soon






       Total’s CEO says work may resume by the end of March, pointing to his company’s security
       agreement with the Mozambican government and insisting production will begin in 2024




        MOZAMBIQUE       PATRICK Pouyanné, the CEO of France’s Total,  quarter we should be able to restart the work,” he
                         has said that his company aims to resume work  was quoted as saying by Bloomberg and other
       WHAT:             on the Mozambique LNG project before the  agencies. “That’s the objective that we set to our-
       Pouyanné says     end of March, and there are indications that his  selves jointly with the government.”
       Mozambique LNG can   optimism is not misplaced. He expressed these
       restart construction on   hopes last week, when he reminded reporters  On site and on schedule
       the Afungi Peninsula soon  that Total had signed a security agreement with  According to press reports, the proposed perim-
                         Mozambique’s government in order to safeguard  eter will include not only the construction site
       WHY:              its construction site on the Afungi Peninsula.  but also related facilities such as a work camp.
       The company and its   The French company and its non-operating   It will also cover the town of Palma and its
       partners have had to   partners in the Mozambique LNG consortium  bay, as well as two islands offshore, and would
       evacuate staff following   have been building a natural gas liquefaction  extend past the town of Olombe in the south. It
       attacks on nearby areas   plant and other onshore facilities supporting the  will not include Mocímboa da Praia, a port in
       by Islamist insurgents  development of gas at the offshore block known  Cabo Delgado that Total and its partners had
                         as Area 1 at the site. However, they evacuated  been using as a delivery point for the equipment
       WHAT NEXT:        most workers in January and have slowed the  needed to build the Mozambique LNG plant on
       If FADM upholds   pace of operations.                  the Afungi Peninsula before losing access to it
       its commitments,    Under the agreement between Total and the  last August.
       Mozambique LNG will   Mozambican government, all areas of the Cabo   Pouyanné also said that Total and its partners
       have a better chance of   Delgado province within 25 km of the site must  hoped to remain on schedule even though they
       beginning production on   be secured by the country’s armed forces, known  had to evacuate around 9,000 workers from the
       schedule in 2024  as Forças Armadas de Defesa de Moçambique  onshore site earlier this year, bringing the size of
                         (FADM). According to Pouyanné, if FADM  the team working at the site down to about 1,000.
                         upholds its part of the deal, the investors will be  The Mozambique LNG consortium is still work-
                         able to achieve their objectives.    ing to drive the offshore and engineering aspects
                           “If, on the ground, the armed forces and the  of the project forward, and plans to bring the
                         police are able to re-control the area that we  liquefaction plant’s first 6.44mn tonne per year
                         agreed together, I think by the end of the first  (tpy) production train on stream in 2024 have































       P4                                       www. NEWSBASE .com                        Week 07  18•February•2021
   1   2   3   4   5   6   7   8   9